A contract has been signed for the construction of the new 11.3-km Batumi–Sarpi road, one of the key sections of Georgia’s East–West Highway.
The signing ceremony was held at the Ministry of Infrastructure of Georgia. Prior to the signing of the contract, Minister of Infrastructure Revaz Sokhadze, Minister of Finance Lasha Khutsishvili, Deputy Ministers of Infrastructure, and Chairman of the Roads Department Levan Darakhvelidze met with representatives of China Railway Tunnel Group Co., Ltd. (CRTG), the company awarded the contract through an international tender. During the meeting, the parties discussed the key stages of project implementation, the organization of construction works, and matters related to ensuring that the project is completed within the specified timeframe and in compliance with the required quality standards.
The contract was signed by Deputy Chairperson of the Roads Department Salome Tsurtsumia and Liang Hongjun, an authorized representative of China Railway Tunnel Group Co., Ltd.
The new Batumi–Sarpi road is the westernmost section of the East–West Highway Corridor. It will connect the Batumi Bypass Highway with the Georgia–Türkiye state border and will form an important part of the transport infrastructure of the Middle Corridor linking Europe and Asia.
The project includes the construction of an 11.3-km two-lane highway, a 7.6-km tunnel, and three bridges, including a 1.47-km-long bridge structure. A 500-metre coastal protection structure will also be constructed. Following the main tunnel of the Kvesheti–Kobi road, the 7.6-km Batumi–Sarpi tunnel will be the second-longest road tunnel in Georgia.
Upon completion of the new road, international and transit traffic will be diverted from Adjara’s densely populated and resort coastal areas to the new highway. As a result, traffic volumes on the existing road and within the resort area will be significantly reduced, road safety will be improved, and travel conditions will be enhanced.
The project value exceeds GEL 809 million, and the construction period is 48 months. The project will be co-financed through a loan from the Asian Development Bank (ADB) and the State Budget of Georgia.
Of the total 428.35 km of the E60–E70 East–West Expressway, 324.75 km have already been opened to traffic. The commencement of construction of the Batumi–Sarpi road marks another important step towards the completion of the expressway and the strengthening of Georgia’s transport and transit role within the Middle Corridor.